Spectrum Traffic Data Inc. Project Hub
Last updated Fri May 22, 2026 · 02:11 UTC
Green
Current phase
Engineering
Started May 15, 2026
Next milestone
Eng. Completion
Target Sep 15, 2026
Target shipment
Nov 30, 2026
EXW Shenzhen · 500 units
Contract value
US$499,564–793,863
Production PO pending after prototype
01 · Milestones

Engagement timeline

1 complete · 1 active · 3 upcoming
01
Engineering Kickoff
May 15, 2026
02
Engineering Completion
Sep 15, 2026
03
Prototype Approval
Sep 30, 2026
04
Production Deposit
Oct 5, 2026
05
Shipment Balance
Nov 30, 2026
02 · Pending POs

Active purchase orders

From CNBS QuickBooks · closed hidden
STD260424-1
US$66,838.50
Engineering Phase · NRE
  • VCU-NREComplete VCU system development
Expected delivery Sep 15, 2026
In Production
03 · This Week

Week ending Sat May 30, 2026

Posted by Daniel Mallen

Shipped this week

Planned next week

Blockers · need client input

  • No outstanding items
04 · Workstream Progress

Engineering workstreams · weighted progress

vs. previous week
PCBA + Linux + Firmware
5%
Was 0% last week · +5
Mechanical
5%
Was 0% last week · +5
Integration & Test
0%
Starts after PCB Rev A bring-up
Project Management
5%
Was 0% last week · +5
05 · Schedule

Phase timeline

May 2026 – Sep 2026
May 2026
Jun 2026
Jul 2026
Aug 2026
Sep 2026
PCB Design R&D
Firmware Dev R&D
Mechanical CAD R&D
Integration & EVT Test
Prototype Build Hardware
Production Run Manufacturing
Shipment Prep Logistics